Scheduling a task
The Schedule Configuration step of the CloudLink Task Manager Wizard lets you determine when and how often a task runs.
You can configure a CloudLink task to run at any of the following times:
-
Immediately
-
Later, either once or recurrently
-
Immediately and also later, either once or recurrently
To schedule a task
-
On the Schedule Configuration wizard page, in the Task Name box, enter a name for the task.
-
Select one of the following options:
-
To run the task immediately, and once only, select Run Immediately , and go to step 5.
-
To run the task later, either once or recurrently, select Enable Schedule.
-
To run the task immediately and also later, either once or recurrently, select Run Now and Schedule for Later.
-
-
In the Start Time boxes select the future date and time to run the task.
-
If you want a scheduled task to recur, do as follows:
-
Under Recurrence, select Repeat Every and then select the frequency with which to run the task.Note: A high frequency such as hourly may incur demands on your network bandwidth.
-
Then under Repeat, specify one the following:| No End Date | The task continues to recur with no end date. || Number of Times | The task runs for the number of times that you select. || Until | The task recurs until the date and time you select. |

-
-
Click Next to continue to the final wizard step.